AC withstand voltage test hi GIS (gas-insulated substation) mantain tur test pawimawh tak a ni. Test himna leh a hlawhtlin theih nan step bikte chu hetiang hi a ni a;
1. Subject dinhmun chu nemnghet rawh .
Installation dik tak .
GIS hmanrua chu a pum puia dah vek tur a ni a, a inzawmtu part zawng zawng (casing leh air chamber ang chi) chu mechanical damage emaw looseness emaw awm lovin uluk taka seal vek tur a ni.
SF6 Gas State ah hian a awm a.
SF6 gas chu rated density-ah fill tur a ni a, leakage a awm loh nan leak test chu tihfel tur a ni.
Gas-a moisture content hian humidity avanga insulation performance a nghawng loh nan standard (150ppm aia tlem emaw a aia tlem emaw) a tlin tur a ni.
Basic Test zawhfel .
Voltage test hmain basic items te chu main circuit resistance measurement leh insulation resistance test ang chi te chu complete la, defect la awm lo a awm loh nan .
2. Non-Test hmanrua isolation .
Device hrang hrang isolated tur range .
High voltage cable, overhead line, power transformer, leh electromagnetic voltage transformer (test circuit hian magnetic saturation a thlen theih chuan isolated a ngai a; frequency modulation series resonant device hman a nih a, voltage standard a inmil chuan a awm reng thei a ni).
Overvoltage venhimna hmanrua, lightning arrester leh spark gap protection te pawh a awm.
Extension hmanga enkawlna .
GIS extension-a voltage test tih a nih chuan, a kianga awm device awmsa chu power off la, breakdown risk awm lohna turin rintlak takin ground rawh.
3. Test loop siam dan tur .
Pressure mode ruahmanna siam a ni.
Test voltage chu phase conductor tin leh housing inkar (Phase{0}}by-phase test) inkarah dah tur a ni a, non-test phase conductor chu ground tur a ni.
Component zawng zawng test voltage pakhat tal a awm theih nan inlet leh outlet bushings hmanga priority pressurization
Stage test dan tur a awm em?
GIS-a power capacity zawng zawng a lian lutuk chuan (entir nan, bus bar sei emaw, structure complex tak emaw), device overload loh nan section hrang hrangah voltage withstand tests nei rawh
4. Hriselna leh venhimna dan .
Environment enfiahna .
Test area chu fences leh warning sign hmanga siam tur a ni a, non-Test personnel te chu an lut tur a ni lo.
Grounding system chu rintlak a nih leh nih loh leh cover-a ground cable zawng zawng chu a inzawm tlat theih nan enfiah rawh.
Thil hmanrua dinhmun enfiah .
Frequency conversion resonance device, voltage divider, protection resistance, leh hmanraw dang status te chu enfiah a ni.
Fracture withstand voltage (disintegrated circuit breaker ang chi) tih i mamawh chuan test scheme hran i ruahman a ngai a ni.
5. Test dan tur Presets .
Advanced Purification buatsaih dan tur .
Experimental phase ni mahse, "sophisticated purification" procedure (voltage tihpun zauh zauh avanga internal conducting particle removal) 1 chu configure hmasak a ngai a ni.
Parameter setting a ni a.
Test voltage value chu set la, GIS rated voltage (35kV, 72.5kV ang chi) a zirin rat,e leh duration te chu boost rawh.